Ørsted, the wind farm Washington stopped twice, and the cushion

Ørsted promised to switch on an American wind farm in the second half of 2026. Washington stopped it twice. It switched on in October.

By Max Noble ·

In 3 lines

  1. Ørsted promised to switch on Revolution Wind, its half-owned American wind farm, in the second half of 2026.
  2. Washington stopped the work twice, a judge restarted it twice, and it switched on in October 2026.
  3. My verdict: the money Ørsted lined up before the trouble is what let it wait.

Friday, 22 August 2025, off Rhode Island. Revolution Wind, a wind farm Ørsted owns half of, has all its foundations down and most of its turbines up when America's offshore regulator orders the work to stop. This column is about one mechanic, the cushion: money lined up before the trouble, so you can wait out a no, and you will spot it before the room does.

The same day, Ørsted put a promise in writing: it aimed to keep building toward “COD in the second half of 2026”, shorthand for switching it on. Keep that sentence.

A wind farm with almost a third of its turbines missing and orders not to finish is, technically, the most expensive set of foundations in New England.

On Thursday I read Ørsted's third-quarter results while my coffee went cold. On 5 November it said Revolution Wind had reached commercial operations in October.

So how does a promise survive two stop orders it did not write? Today's law: keep owners willing to write the next cheque. Hold on.

This one had already slipped a year from its first date, 2025. Eleven days before the stop order, Ørsted had announced a plan to ask its owners for fresh money. It may be the only umbrella in corporate history ordered eleven days before the rain.

Most companies look for money when trouble arrives, at that day's price. A cushion is money lined up before the trouble, so the company can afford to wait while somebody else decides. So when somebody else can stop a promise, ask how long the company could afford to wait.

In October the owners answered: a rights issue, new shares sold to existing owners, raised about DKK 60bn ($9.4bn). The Danish state, which owns half of Ørsted, took its full half.

On 22 September 2025 Judge Royce Lamberth let the work restart. On 22 December the regulator paused it again, and on 12 January the same judge said go again. By January it was the only building site in New England with a judge for an on switch.

Page 4 of Ørsted's first-quarter report for 2026 said Revolution Wind “remains on track to commissioning in the second half of 2026”.

The danger was printed too, on page 26: a “continued risk of imposed construction delays outside of Ørsted's control”. Most companies print that sentence to protect themselves. Ørsted printed it with the umbrella already in the hall.

The last turbine went up in September 2026, and the farm can now power about 350,000 homes.

Here is the cold part.

Nobody here is accused of anything. In fairness, it was not free: the same report cut the value Ørsted puts on the project by about DKK 260mn ($39mn), and a US government request to cancel its earlier federal approval, filed in a case brought by opponents, still awaits Judge Lamberth. A promise kept on time can still arrive with an invoice.

Right of reply: Ørsted had not been asked for comment before publication on 8 November 2026. Any response will be added here, with the date it arrived.

The crews at sea and on the pier in New London went back to work twice. The money helped make sure there was work to go back to.

Three signals to watch: a promise somebody outside can stop; money lined up before the stop; the danger printed plainly in the report.

My verdict: Ørsted promised a date it did not control, then had the money to outlast the people who did.

What you now know

  • A promise somebody else can stop is only as good as the money that pays for the wait.
  • Look for money lined up before the trouble: in calm weather it is a cushion, in a storm it is a rescue.
  • Read the risk page: when a company names the danger plainly and has already paid for it, its promise has a chance.

Send this column to a colleague →

A cushion is the only part of a business plan you hope never to sit on. Ørsted sat on it twice.

Keep that sentence, I said. Washington tried to take it away twice; Ørsted kept it, and handed it back in October.

Ørsted's next American promise, Sunrise Wind, is about 60 per cent built and due to switch on in the second half of 2027; it is in my diary. Next in my queue: Ford, and the two cents of every dollar that went missing.

Law No. 12 · Keep Owners Willing to Write the Next Cheque

Understand Business. Better.
Max Noble

The verdict

Ørsted promised a date it did not control, then had the money to outlast the people who did.

Tomorrow

Ford, which promised to keep eight cents of every dollar it sold, and the two cents that went missing.

Get tomorrow’s column in your inbox →

Before your first meeting

Get the column in your inbox.

One company, one law, every morning, with the Morning Brief on Monday and Thursday. Free.

Unsubscribe any time. Not investment advice.

Words Kept
“COD in the second half of 2026”
Ørsted company announcement on the Revolution Wind stop-work order, 22 August 2025
PromisedAugust 2025·DeliveredOctober 2026 (announced 5 November 2026)

Stopped twice. Switched on in October. The cushion did the waiting.

🇩🇰 Denmark · Renewable energy
Rasmus Errboe
KEPTswitched on October 2026
Rasmus Errboe
Group President & CEO, Ørsted, since 1 February 2025
Photo: Ørsted (press kit)
ØrstedDenmark · Renewable energy

The writer lectures in strategy, finance and innovation, spent more than a decade in internal controls around the world, and is the founder of Max Noble, which tracks broken corporate promises and how giants rise and why they fall.

Not investment advice · Anyone charged is presumed innocent until a court decides otherwise · DKK 6.71 to the dollar (6 November 2026); the rights issue at the rate reported in October 2025 · Max Noble holds no stake in any party named · Published 8 November 2026, 06:05 Copenhagen.

How this column was judged

  1. What was promisedRevolution Wind to keep building toward “COD in the second half of 2026”, on the day the US stop-work order arrived (22 August 2025)
  2. Where it was saidorsted.com
  3. What came outRevolution Wind “reach[ed] commercial operations” in October 2026, after two stop orders and two court rulings (October 2026 (announced 5 November 2026))
  4. Where it came outorsted.com
  5. The verdictKept · Law No. 12 · Keep Owners Willing to Write the Next Cheque

The numbers, exactly

  • Stop-work order, 22 August 2025: Revolution Wind 80% complete, all offshore foundations installed, 45 of 65 turbines installed · source
  • Rights issue, October 2025: 894,298,680 new shares at DKK 66.60 (ratio 15:7); the Danish State subscribed 451,522,164 shares, about 50.1% · source
  • Rights issue gross proceeds DKK 59.56bn (about EUR 7.98bn; $9.4bn as reported at the time) · source
  • New shares at about DKK 66 against a market price of about DKK 120 at the time · source
  • Q1 2026 report: Revolution Wind construction 94% complete (p. 4); impairment of DKK 260mn on Revolution Wind in Q1 2026 (p. 25), about $39mn at DKK 6.71 · source
  • Revolution Wind: 704 MW from 65 turbines, enough for about 350,000 homes; Sunrise Wind about 60% complete (Q3 2026 report) · source

Sources

  1. Ørsted company announcement: Revolution Wind receives offshore stop-work order from BOEM (80% complete, all foundations, 45 of 65 turbines; aim of COD in the second half of 2026; rights issue announced 11 Aug 2025), 22 Aug 2025
  2. Ørsted company announcement: Q3 2026 results; Revolution Wind and Borkum Riffgrund 3 reach commercial operations (Revolution Wind in October 2026), 5 Nov 2026
The full notes · 11 more sources
  1. Ørsted company announcement: Result of rights issue (Danish State subscribed 451,522,164 new shares, about 50.1%), 6 Oct 2025
  2. offshoreWIND.biz: Ørsted raises EUR 7.98bn in oversubscribed rights issue (most proceeds for Sunrise Wind; financial flexibility), 7 Oct 2025
  3. Maritime Executive: Ørsted raises $9.4bn in heavily discounted rights issue (new shares at DKK 66 against about DKK 120), 7 Oct 2025
  4. WBUR: Judge Royce Lamberth lifts the stop-work order on Revolution Wind, 22 Sep 2025
  5. Offshore Magazine: court allows Revolution Wind to resume construction (BOEM suspension of 22 Dec 2025; injunction 12 Jan 2026), 13 Jan 2026
  6. Ørsted interim financial report Q1 2026: p. 4 Revolution Wind 'remains on track to commissioning in the second half of 2026', 94% complete; Sunrise Wind commissioning in second half of 2027; p. 25 Revolution Wind impairment DKK 260mn; p. 26 'continued risk of imposed construction delays outside of Ørsted's control'
  7. CT Mirror: Revolution Wind now fully operational (final turbine September 2026; about 350,000 homes; State Pier, New London; Sunrise Wind about 60% complete; Interior request pending before Judge Lamberth), 5 Nov 2026
  8. Utility Dive: DOJ moves to revoke offshore wind permits (Revolution Wind motion filed in a case brought by ACK for Whales and Green Oceans), 22 Oct 2026
  9. Wikipedia: Revolution Wind (50:50 Ørsted and Skyborn Renewables; 704 MW; original 2025 target delayed a year)
  10. Ørsted press kit: executive team portraits (Rasmus Errboe)
  11. Pound Sterling Live: USD/DKK history 2026 (close 6.7094 on 6 Nov 2026)

Readers’ page 47

Found a warning nobody read?

Every company prints its troubles somewhere. Usually on a page nobody reaches. Send me the page. If it says what you say it says, I will credit you by first name in a column.

Your email is only used to reply to you. I check every page before anything is printed.

Thank you. I will read it, which already puts me ahead of the board.